HobbsUpchurch.com | 1-800-849-1861            Home | Company Profile | News | Contacts | Awards | Job Postings
   Hobbs, Upchurch & Associates, P.A.
 Superior Performance Through Innovative Design
 Water | Wastewater | Grants & Funding | Geographic Information | Site Development | Transportation | Surveying
 
Wastewater Pump Stations and Sewer Lines Printable Page

Hobbs, Upchurch & Associates has participated in the planning, design, and construction of numerous sewer line extensions, sewer line replacements, and wastewater pump stations. Following is a brief summary of some of our sewer line and pump station projects.

North Carolina Department of Correction, Anson County, North Carolina


The new station was designed to serve the new prison and two existing prisons, a total of 2,200 beds. The design required the pump station to discharge to an existing 6-inch force main, which created significant high head conditions. The 30 HP pumps in the new station operate in series at 525 gallons per minute at 200 feet of head. A total of four pumps were needed to provide the redundancy required by the State. The existing backup generator is being used to provide standby power for the new pump station.

Sewer Service to Town of Peachland


Funding acquisition, design, project administration, and construction inspection for county sewer extension to the Town of Peachland. The project included an evaluation to determine current and future flows into the collection system to ensure the long-term needs of the area would be met. The design included 15,500 linear feet of 10-inch of gravity sewer, a 240 gpm sewer pump station, and 4,000 linear feet of 6-inch force main.

Burlington, North Carolina Influent Pump Station Rehabilitation


Planning, surveying, engineering design, and construction management for a project to upgrade and modify the existing influent pump station at the South Burlington Wastewater Treatment Plant. The project included the replacement of existing 125 HP pumps with new 225 HP variable frequency drive pumps, as well as the replacement of the original 16-inch suction line and gate valves from the wet well and the 16-inch check valves and 16-inch discharge gate valves on the pump discharge. The existing 30 inch header was also recommended for replacement.

New Sewer Collection System, Calypso, North Carolina


HUA helped the Town obtain over $3 million in grant funding from the North Carolina Rural Center and from the CDBG Infrastructure program. The project included layout, design, and permitting of a new sewer collection system to serve the Town of Calypso. The Calypso collection system will discharge to the wastewater treatment facility in the Town of Mount Olive. Calypso has experienced significant problems with failed septic systems caused by poor soil conditions and shallow water tables. As part of the sewer design HUA evaluated the current flow conditions and the sewer needs over the 20-year planning horizon. The new system includes three pump stations , 30,000 linear feet of gravity sewer lines, and approximately 23,000 linear feet of force mains. Each of the pump stations will be equipped with an on-site backup generator. In addition, the primary pump station into the Mount Olive sewer system will include flow metering for billing purposes.

Camp Lejeune, North Carolina


Replace Pump Station AS629. The new pump station includes a new cast in place wet well, influent trough with 12-inch comminutor, a manual bypass bar screen, four 15 HP submersible centrifugal pumps. The wet well is divided into two sides with two pumps in each side and isolation slide gates capable of diverting flow to either side for maintenance on pumps in wet well if necessary. The pump station is equipped with an on-site standby generator as required by Camp Lejeune design standards.

Piney Green Road Pump Station Replacement and Sewer Improvements. Design of 7,000 linear feet of new 8-inch gravity sewer and a new 180 gpm pump station. The project eliminated six existing pump stations that were located along Piney Green Road. The flow from each of the lift stations was combined to the new lift station completed by HUA. The Piney Green Road Pump Station was equipped with an on-site backup generator with underground fuel tank.

STT Area, Pump Station Replacements. Design of three new wet pit/dry pit pump stations with comminutors to replace one existing 180 gpm pump station and two existing 320 gpm pump stations. Each pump station was equipped with a backup generator and underground fuel tank.

Bldg. 85 Pump Station Replacement. Design of one new wet pit/dry pit pump station with comminutor to replace an existing 180 gpm pump station. The new pump station was equipped with an on-site standby generator with an underground fuel tank.

Hadnot Point, Beach Area, and Rifle Range Force Main. Provided civil engineering design services for the replacement of force mains and gravity sewer lines in the Hadnot Point, Beach Area and Rifle Range Areas of Camp Lejeune. Projects included design of over 128,388 LF of 3 inch to 36 inch sewer line, including pump stations, manholes and services.

Highway 401 Sewer Project, Hoke County, North Carolina


Design and construction management of a sewer extension project to serve the Highway 401 business corridor. The project included one 350 gallon per minute above-ground lift station, 4,500 linear feet of 15-inch gravity sewer, 6,500 LF of 12-inch gravity sewer, and 2,500 LF of 8-inch sewer force main. The project also included valves, piping, motor control center with heavy duty thermal-magnetic circuit breakers, magnetic motor starters, radio telemetry, automatic pump controls, and all related appurtenances in a concrete block structure constructed over a new 10 foot diameter precast concrete wet well. The project also included an on-site emergency generator. The lift station was designed to accommodate business and residential growth in the Highway 401 area. Significant planning and coordination with the North Carolina Department of Transportation was required, as the project was constructed within the right-of-way of a road.

Silver City Sewer Project


Planning, funding, surveying, design, plans, specifications, permitting, cost estimates, and construction coordination. Hobbs, Upchurch & Associates worked with Hoke County to obtain approximately $1.1 million in funding to extend sewer service to the Silver City Community. The community had significant health problems caused by failing septic systems. These failures were documented by HUA as part of the preliminary engineering process. The project is regional in that sewer treatment will be provided by the City of Raeford. HUA completed the surveying, easement acquisition, engineering design, permitting, and construction inspection for 20,000 LF of 8 and 12-inch sewer mains to serve 120 low and moderate income homes.

KCI Pump Station and Force Main Project, Kershaw, South Carolina


Installation of approximately 34,446 LF of 8 inch force main, 15 LF of 6 inch force main, approximately 1,016 LF of 8 inch gravity sewer, five five manholes, upgrading an existing duplex submersible pump station to 600 gpm, upgrading an second duplex submersible pump station to 200 gpm, and one new 200 gpm duplex submersible pump station.

Lancaster County Water and Sewer District, South Carolina


Bear Creek Sewer Outfall. Scope consists of approximately 16,500 LF of 15" and 18" gravity sewer outfall, pump station and force main to service the existing community of Elginwood, several proposed developments, and projected flows for a 12,000 acre drainage basin. This project also evaluates two possible scenarios for routing the discharge to the City of Lancaster's' WWTP based upon capacity of existing infrastructure and proposed capital improvements of downstream sewers.

Woodland Hills Sewer Improvements. Design assistance, permitting and administration of Woodland Hills Sewer Improvements project for Lancaster Water and Sewer District. Project included 15,500 LF of 8 inch sanitary sewer, 2,500 LF of 4 inch force main and 120 GPM pump station.

Inflow and Infiltration Rehabilitation Project,Lancaster County Water and Sewer District, South Carolina


This SRF loan will result in approximately 576 LF of dig up and replace of existing 6 inch sewer with new 6 inch sewer, 3,282 LF of dig up and replace of existing 8 inch sewer with new 8 inch sewer, 3,485 LF of dig up and replace of existing 10 inch sewer with new 10 inch sewer, 2,323 LF of dig up and replace of existing 15 inch sewer with new 15 inch sewer, 65 LF of dig up and replace of existing 18 inch sewer with new 18 inch sewer, 27 - 4 inch sewer service reconnections 2 manholes, miscellaneous street repairs, 4,311 LF of 8 inch sewer to be internally reconstructed with Cured-In-Place methods, 923 LF of 10 inch sewer to be internally reconstructed with Cured-In-Place methods, 498 LF of 15 inch sewer to be internally reconstructed with Cured-In-Place methods, sewer service reconnections, manhole inserts.

Rehabilitation of Pump Station No. 1, Lumberton, North Carolina


HUA completed the preliminary evaluation, design, and construction management for the upgrade to the City's primary sewer lift station. The station pumps 15 MGD and is located next to the Lumber River in the center of the City. The Public Works Staff has experienced problems with overflows and near-overflows during rainfall and flood events. Significant complications arose during the flooding that resulted from Hurricane Floyd. HUA worked with the Town to obtain project funding through FEMA and through the Clean Water Management Trust Fund.

The three original end suction centrifugal pumps were replaced with two new 6,700 gpm, 50 hp submersible pumps. The project required the construction of a new wet well and coordination with the contractor to ensure the existing station remained in service during construction. In addition, the design had to incorporate the existing electrical service and the existing on-site backup generator. The project also included the installation of guide rails, piping, valves, pump controls, across the line motor starters, level sensing, disconnects, conduit, power wiring, and control wiring. The contract required the removal of existing pumps, piping, valves, electrical controls, etc. as necessary to perform a complete installation. The contract also included the provision of bypass pumping necessary to maintain the pump station in operation while the pump replacement was ongoing.

Monroe, North Carolina, Various Pump Station and Annexation Projects


Rocky River Road Annexation. Design of 12,909 linear feet of 12-inch and 8-inch gravity sewer, 58 manholes, 8,847 linear feet of 6-inch PVC force main and 180 gpm pump station to serve Rocky River Road annexation area. The project included an on-site backup generator for standby power.

Highway 200 and Highway 601 Annexation Project. The design of 12,000 linear feet of 12-inch and 8-inch gravity sewer along with a 340 gpm pump station to serve the newly annexed project area. This project also included the design of 8, 000 linear feet of 6-inch PVC water main. The pump station included a standby power generator.

Monroe Airport Industrial Park. Analysis, design and construction administration of the sewer infrastructure to serve the proposed park. Analysis included coordination of purchase of 8,000 linear feet of 12-inch gravity sewer from the County and upgrade of an existing pump station. Design included 8,000 linear feet of 8-inch force main and a 30 HP duplex submersible pump station. The project included design of an on-site generator for standby power.

Steel Street Sewer Main. Design of 234 LF of 16 inch, 2,618 LF of 12 inch and 1,354 LF of 8 inch sanitary sewer mains and 20 manholes to serve Steel Street, Secrest Shortcut, and Outfall "H" Sewer Extensions.

Mt. Gilead, North Carolina, Miscellaneous Pump Station Projects


WWTP Effluent Pump Station. Design and construction services related to 1.5 mgd effluent pump station and 3 miles of 12 inch force main as portion of wastewater treatment plant project.

Highway 109 Pump Station. Design and construction management of sanitary sewer improvements to serve Highway 109 target area. Project included 100 gpm pump station, gravity collection lines and 4-inch force main. The pump station was equipped with on-site standby power.

Highland School Sewer. Designed and managed construction of sanitary sewer improvements to serve Highland School area. Project included 200 gpm pump station, gravity collection lines and 6 inch force main. The pump station included an on-site emergency power generator.

Homanit USA Sewer. Design of a 320 gpm Pump Station along with 8,500 linear feet of 8-inch PVC force main, and 1,200 linear feet of 8-inch gravity sewer to serve the new Homanit USA fiber board plant. The pump station included an emergency standby power generator.

Oak Island, North Carolina, Sewer Service to Business District


HUA worked with the Town to obtain funding through the Clean Water Bond High-Unit Cost grant program to construct a new sewer collection system in the downtown business district. The area was severely limited by poor soil conditions and failed septic systems. The project included the design of 13,000 linear feet of 15 inch, 12 inch, and 8 inch gravity sewer to serve the business district of Oak Island. This project included one 320 gpm pump station and one 180 gpm pump station along with 10,000 linear feet of 8 inch and 6 inch sewer force main. Both pump stations included backup power generators.

COMTech Pump Station and Force Main, Pembroke, North Carolina


Project involves the construction of sewer mains and above-ground pump stations to serve the Carolina Commerce and Technology Center (COMTech). COMTech will be a high-tech, professional, commercial and light industrial business park southeast of the Town of Pembroke on Highway 711. HUA worked with the Town to obtain over $1.8 million in grant funding from the North Carolina Rural Center, the CWB Industrial Development Fund, and the Economic Development Agency to help fund the project. The project includes 2, 200 LF of 15 inch gravity sewer, 17,200 LF of 12 inch gravity sewer, 2,200 LF of 6 inch force main, and 5,900 LF of 4 inch force main. The project also includes the construction of three new pump stations and the upgrade of one existing submersible pump station.

Southern Pines, North Carolina


HUA has completed the design, permitting, and construction management for multiple sewer system projects in Southern Pines. The following summarizes some of the projects completed.

Maples Pump Station Replacement and Force Main. The existing Maples Pump Station was an old pneumatic ejector type, enclosed in a below ground steel structure. The existing steel structure had deteriorated and the structural integrity was of concern. Also, the existing equipment was old and worn and the ability to find replacement parts hampered routine maintenance. The station was replaced with a new concrete wet well and submersible non-clog sewage pumps. This station was equipped with a separate valve vault for easy maintenance. The project also included 67 linear feet of new 6-inch PVC force main to tie into an existing 6-inch force main, 34 linear feet of new 8-inch PVC sanitary sewer main, and one new doghouse manhole to connect to the new wet well.

Ridgeview Pump Station Replacement. The original Ridgeview pump station pump station was equipped with pneumatic ejector type pumps. The station was in poor condition and required replacement. HUA completed the design and construction management for the replacement project. The new pump station included a new wet well and 180 gallon per minute submersible grinder sewage pumps. The project also included new sewer force main to complete connections into the collection system. The old pump station was demolished and removed as part of the construction project.

Elks Club Pump Station and Force Main. The existing Elks Club Pump Station originally included an old concrete wet well with submersible pumps and a dilapidated above-ground structure. The original pump station was replaced with a new concrete below wet well and 180 gallon per minute submersible sewage pumps. The project also included 750 linear feet of new 6-inch PVC force main and 80 linear feet of 12 inch steel casing bored under CSX Railroad. The new 6-inch force main ties into existing 8-inch gravity sewer. Approximately 800 linear feet of new 8 inch PVC sanitary sewer main and 4 new manhole were required to connect to the new wet well.

New Sewer Collection System, Stem, North Carolina


Hobbs, Upchurch completed a preliminary study to document failed septic systems and contaminated groundwater supply wells in Stem, North Carolina. The study helped obtain $2.8 million in grant funding from the North Carolina Rural Center for the construction of a new sewer collection system in the Town of Stem. The Stem collection system will discharge to the sewer system in the Town of Butner for treatment. The project includes surveying, design, grant management, and construction management for five new pump stations, 18,000 linear feet of gravity sewer, and over 26,000 linear feet of sewer force main.

New Sewer Collection System, Wagram, North Carolina

HUA helped the Town of Wagram obtain $3,000,000 in grant funding through the Rural Center Unsewered Communities program for the construction of a public sanitary sewer system. The engineering design required evaluations of current conditions, as well as evaluations of future sewer needs over the 20-year planning horizon. The project includes 39,000 linear feet of 8-inch, 10-inch and 12-inch gravity sewer, three sewer pump stations, and 15,000 linear feet of 6-inch PVC and DIP force main. Two of the three pump stations include 5 HP, 180 gallon per minute, above-ground pumps. The third pump station has a higher head requiring 7.5 HP, 180 gallon per minute pumps. All of the pump stations are equipped with backup power generators. The Wagram sewer collection system discharges to a regional wastewater treatment facility at the Laurinburg-Maxton Airport Commission.

Back - Wastewater Master Plans and Studies Wastewater Introduction

 

Water | Wastewater | Grants & Funding | Geographic Information | Site Development | Transportation | Surveying

 

Southern Pines - Hampstead - Nags Head - Charlotte - Beaufort
Copyright Hobbs, Upchurch & Associates, P.A. 2004
info@hobbsupchurch.com